Nature Valley Road Project – Update

The town was notified that Clemens Excavating is preparing to start construction in the Nature Valley Subdivision on Monday, July 29th.  This will include some erosion control setting, some ditching and setup for equipment.

 

The week of Monday, August 5th, Clemens Excavating will start removing the blacktop and installing culverts and storm water lines.  At this point of the project, sections of the road may be closed for some time during the day while culverts are being put in place.  The area and timing of closures will be dictated by where the work is being performed. 

 

The estimated completion date is Monday, August 26th or sooner, depending on the weather. Please contact the office with any questions or concerns so they can be addressed while the crew is onsite. 

 

Your cooperation regarding this project is appreciated.

 

Sincerely,

 

 

Kathleen Clark

Town of Vienna Clerk